When a contractor or subcontractor is terminated for default, the terminating party may seek its damages for completing the defaulted contractor or subcontractor’s scope of work. The cost to complete the work will almost always exceed whatever money was left in the contract to complete the work.

Construction contracts will often expressly allow the terminating party to obtain the above excess completion costs. And under Florida law, “controlling weight should be given to the actual expenditures, made in good faith, that are necessary to complete the job covered by the original contract.” R.K. Cooper Builders, Inc. v. Free-Lock Ceilings, Inc.

But what happens when the excess completion costs include the cost to construct a second building when only one building was contemplated under the parties’ contract?

Will those excess completion costs be considered a form of consequential damages that may be barred under the parties’ contract? A federal court recently considered that question in United States ex rel. Sustainable Modular Management, Inc. v. JE Dunn Construction Company.Continue Reading Does a Consequential Damages Waiver Bar the Recovery of Completion Costs?

When a contractor bids a job, it does so based on a planned sequence of work and productivity of job labor. There are many issues that can arise while building a project that affect labor productivity, and many of those issues are not the contractor’s responsibility. The terms of the contract will often dictate whether a loss of productivity is compensable.

A contractor that suffers a loss of productivity may be entitled to additional compensation. Many methods have been used to calculate loss-of-productivity damages.

In JH Kelly, LLC v. AECOM Technical Services, Inc., a federal court recently considered several different methods for calculating a loss of productivity on a project.Continue Reading Three Ways to Potentially Calculate Lost Productivity Damages

To win on a breach-of-contract claim, the party asserting the claim must prove that the other party to the contract caused the non-breaching party to incur damages. In construction disputes, the non-breaching party (e.g., a contractor or subcontractor) will often claim that it incurred lost profits due to the other party’s breach.

For example, if an owner wrongfully terminates a contractor, the contractor may be entitled to the profit that it was going to make on the project but for the owner’s termination of the contract. But to obtain those lost profits, the contractor will have to offer supporting evidence.Continue Reading How to Prove Lost Profits in Construction Disputes

I write a fair amount about construction claims, and I frequently emphasize the importance of properly proving damages in connection with construction claims (e.g., a general contractor only being awarded $22,000 on its $1.3 million claim against a subcontractor, in part, because the general contractor failed to adequately prove its damages).

Under Florida law, the burden is on the party seeking damages to prove its damages with a reasonable degree of certainty. While difficulty proving your damages may not be a bar to recovery, the award of damages cannot be based on mere speculation or guesswork.

A recent federal court trial illustrates the difficulty contractors and subcontractors can have proving claims against each other for breach of a construction contract.Continue Reading The Burden of Proof for Construction Damages

If a contractor is unable to perform its work as efficiently as expected due to the actions of other project participants, the contractor may incur loss of productivity damages. There are many ways to price those types of damages. Some methods are better than others, but the least accepted method is the total cost method.

Under the total cost method, the contractor shows the amount it cost to complete its work and subtracts the contract amount. For example, if the contract amount was $10 million, but it cost the contractor $15 million to complete its work, the contractor might claim that it is owed $5 million.

Courts frequently reject the use of the total cost method because it does not take into account damages that are the result of the contractor’s unrealistic bid or the contractor’s own improper performance of its work.Continue Reading Subcontractor’s Modified Total Cost Claim Allowed to Proceed to Trial

There are many ways a project owner or contractor can breach a construction contract. The following is a list of the six most common types of claims a contractor may assert against an owner or a subcontractor might make against a prime contractor:

1. Payment claims: One very common dispute is where the owner fails to timely pay the prime contractor or the prime contractor does not pay a subcontractor on time. Cash flow is very important in construction. If the owner does not timely pay the prime contractor, then the prime contractor may have difficulty paying its subcontractors and the subcontractors may not be able to pay their sub-subcontractors and/or suppliers.

Many times, payment disputes turn on whether the owner had a valid reason for withholding funds from the contractor. For example, if the contractor has submitted a payment application for deficient work, then the owner should not have an obligation to pay for that work. But if it turns out that the work was not deficient, then the owner may have breached the contractor by not timely paying the contractor.

Continue Reading The Six Most Common Contractor Claims

There are two types of differing site condition claims–Type I and Type II claims. Generally, a contractor may make a Type I differing site condition claim where the contractor encounters a subsurface or latent physical condition at the project site that differs materially from the conditions indicated in the parties’ contract.

Under a Type II claim, a contractor may assert a DSC claim where there are unknown and unusual physical conditions at the project site that differ materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the parties’ contract.

Both Type I and Type II DSC claims can be difficult to prove. Last week, after having a seven-day trial, a federal court rejected a subcontractor’s $2.4 million DSC claim in Phillips & Jordan, Inc. v. United States.Continue Reading Federal Court Rejects Subcontractor’s $2.4 Million Differing Site Condition Claim

When unanticipated conditions impact a contractor’s ability to perform its work as efficiently as expected, the contractor may consider pursuing a lost productivity or inefficiency claim. There are many ways to price or calculate a contractor’s inefficiency claim damages, some of which can be quite “creative.” Despite the temptation to calculate inefficiency damages in a manner that will create the biggest claim possible, contractors are best served to make their claims as accurate as possible. That is especially true when a contractor must submit its claim to a government owner such as the federal government. In a very recent case, Lodge Construction, Inc. v. United States, the contractor learned its lesson the hard way regarding the submission of inflated inefficiency claims to the government.

In Lodge, the United States Army Corps of Engineers awarded a project to a contractor to rehabilitate a levee in South Florida, which was part of the Corps’ overall “Everglades Update” restoration mission. During construction, the contractor’s cofferdam breached in two sections, flooding the project site. Later, the contractor submitted several claims to the government for three alleged conditions that impacted the contractor’s performance, including constructive changes to the contract specifications and a differing site condition. The contracting officer denied those claims, and the contractor appealed the decisions by filing lawsuits with the United States Court of Federal Claims. Those lawsuits were consolidated, and a five-day bench trial was held regarding the contractor’s claims.

After the trial, the court issued a 46-page opinion in which the court essentially threw out the contractor’s nearly $4 million in collective inefficiency claims against the federal government, because the court found the contractor’s claims were fraudulent. In particular, the court concluded that the contractor’s claims were fraudulent in at least four ways:Continue Reading How NOT to Price an Inefficiency Claim

Many construction payment disputes come down to one key question—who is responsible for extra costs incurred while building a project? Parties frequently have competing breach-of-contract actions that focus on who is liable. But a recent federal court case shows that you should not give short shrift to the damages that flow from the alleged breach.

In Barlovento, LLC v. AUI, Inc., Civ. No. 18-1112 GJF/JHR, 2021 WL 3879072 (D.N.M. Aug. 31, 2021), the United States Air Force awarded a general contractor a $5.5 million contract to renovate a taxiway at a military base. The general contractor then subcontracted the removal and replacement of the taxiway pavement and base course. This required the subcontractor to place three layers – subgrade, base course, and concrete.

The subcontractor fell behind in its performance of the work, and ultimately, the general contractor held a meeting with the subcontractor and a potential replacement subcontractor that would perform almost all the remaining work. At that meeting, the general contractor announced that it would take the concrete paving work away from the subcontractor. Despite the decision to de-scope the original subcontractor, the general contractor ended up terminating the subcontractor for default.Continue Reading General Contractor Awarded $22,000 of Its $1.3 Million Claim Against a Subcontractor

In Cano, Inc. v. Judet, the Florida Fourth District Court of Appeal recently reaffirmed that when a contractor breaches a contract and the owner sues for breach of contract, the owner has three options for calculating its damages as follows:

  1. the owner may obtain the difference between the contract price and the additional money the owner spent to complete the project; or
  2. the owner can seek the difference between the value the construction would have had if completed and the value of the construction that had been performed before the contractor was terminated; or
  3. the owner can treat the contract as void and seek damages that will restore the owner to the position it was in before entering into the contract.

Courts refer to the first two options as the benefit-of-the-bargain remedy, which is intended to put the non-breaching party in the position it would have been in had the contract been completely performed.Continue Reading Project Owner Damages When the Contractor Breaches a Construction Contract