As I have stated before, differing site condition claims remain fairly common. They can also one of the most difficult claims for a contractor to prove at trial. There are two types of differing site condition claims–Type I and Type II.

Generally, a contractor may make a Type I differing site condition claim where the contractor encounters a subsurface or latent physical condition at the project site that differs materially from the conditions indicated in the parties’ contract.

Under a Type II claim, a contractor may assert a differing site condition claim where there are unknown and unusual physical conditions at the project site that differ materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the parties’ contract.

The United States Court of Federal Claims recently considered a contractor’s $10.5 million differing site condition claim in Nova Group/Tutor-Saliba, Joint Venture v. United States.Continue Reading Contractor’s $10.5 Million Differing Site Condition Claim Torpedoed

Contractor claims for differing site conditions remain fairly common. There are two types of DSC claims. Under a Type I claim, a contractor can obtain additional time and compensation where the contractor encounters a subsurface or latent physical condition at the project site that differs materially from the conditions indicated in the parties’ contract.

For example, contractors have successfully asserted Type I claims where the contractor encountered a groundwater table that was higher than indicated in the contract documents while performing underground work.

With a Type II claim, a contractor may be entitled to additional time and compensation where there are unknown and unusual physical conditions at the project site that differ materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the parties’ contract.

An example of a Type II condition may be where a contractor performing a job that requires soil work encounters tough soils that are more difficult to excavate than expected and no bidder, no matter how experienced, would have anticipated the conditions actually found.

If a contractor believes it is entitled to additional time and compensation on a project due to a DSC, the contractor should consider submitting a claim. There are four things a contractor should know about DSC claims:Continue Reading Four Things to Know About Differing Site Condition Claims

There are two types of differing site condition claims–Type I and Type II claims. Generally, a contractor may make a Type I differing site condition claim where the contractor encounters a subsurface or latent physical condition at the project site that differs materially from the conditions indicated in the parties’ contract.

Under a Type II claim, a contractor may assert a DSC claim where there are unknown and unusual physical conditions at the project site that differ materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the parties’ contract.

Both Type I and Type II DSC claims can be difficult to prove. Last week, after having a seven-day trial, a federal court rejected a subcontractor’s $2.4 million DSC claim in Phillips & Jordan, Inc. v. United States.Continue Reading Federal Court Rejects Subcontractor’s $2.4 Million Differing Site Condition Claim

When unanticipated conditions impact a contractor’s ability to perform its work as efficiently as expected, the contractor may consider pursuing a lost productivity or inefficiency claim. There are many ways to price or calculate a contractor’s inefficiency claim damages, some of which can be quite “creative.” Despite the temptation to calculate inefficiency damages in a manner that will create the biggest claim possible, contractors are best served to make their claims as accurate as possible. That is especially true when a contractor must submit its claim to a government owner such as the federal government. In a very recent case, Lodge Construction, Inc. v. United States, the contractor learned its lesson the hard way regarding the submission of inflated inefficiency claims to the government.

In Lodge, the United States Army Corps of Engineers awarded a project to a contractor to rehabilitate a levee in South Florida, which was part of the Corps’ overall “Everglades Update” restoration mission. During construction, the contractor’s cofferdam breached in two sections, flooding the project site. Later, the contractor submitted several claims to the government for three alleged conditions that impacted the contractor’s performance, including constructive changes to the contract specifications and a differing site condition. The contracting officer denied those claims, and the contractor appealed the decisions by filing lawsuits with the United States Court of Federal Claims. Those lawsuits were consolidated, and a five-day bench trial was held regarding the contractor’s claims.

After the trial, the court issued a 46-page opinion in which the court essentially threw out the contractor’s nearly $4 million in collective inefficiency claims against the federal government, because the court found the contractor’s claims were fraudulent. In particular, the court concluded that the contractor’s claims were fraudulent in at least four ways:Continue Reading How NOT to Price an Inefficiency Claim