Constructive acceleration occurs when a project owner requires the contractor to comply with the original completion deadline, even though the contractor has encountered an excusable delay.

Some courts have held that there are three “essential elements” of a constructive acceleration claim: (1) the contractor encountered an excusable delay, (2) the owner issued an acceleration order, and (3) the contractor incurred additional costs to accelerate its work.

Sometimes there are disputes about whether the owner or prime contractor issued an acceleration order.

Recently, a federal court considered whether a subcontractor adequately alleged a constructive acceleration claim against a prime contractor, which included a discussion of implied acceleration orders.Continue Reading What Is Constructive Acceleration on a Construction Project?

There are many ways a project owner or contractor can breach a construction contract. The following is a list of the six most common types of claims a contractor may assert against an owner or a subcontractor might make against a prime contractor:

1. Payment claims: One very common dispute is where the owner fails to timely pay the prime contractor or the prime contractor does not pay a subcontractor on time. Cash flow is very important in construction. If the owner does not timely pay the prime contractor, then the prime contractor may have difficulty paying its subcontractors and the subcontractors may not be able to pay their sub-subcontractors and/or suppliers.

Many times, payment disputes turn on whether the owner had a valid reason for withholding funds from the contractor. For example, if the contractor has submitted a payment application for deficient work, then the owner should not have an obligation to pay for that work. But if it turns out that the work was not deficient, then the owner may have breached the contractor by not timely paying the contractor.

Continue Reading The Six Most Common Contractor Claims