As I have stated before, differing site condition claims remain fairly common. They can also one of the most difficult claims for a contractor to prove at trial. There are two types of differing site condition claims–Type I and Type II.

Generally, a contractor may make a Type I differing site condition claim where the contractor encounters a subsurface or latent physical condition at the project site that differs materially from the conditions indicated in the parties’ contract.

Under a Type II claim, a contractor may assert a differing site condition claim where there are unknown and unusual physical conditions at the project site that differ materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the parties’ contract.

The United States Court of Federal Claims recently considered a contractor’s $10.5 million differing site condition claim in Nova Group/Tutor-Saliba, Joint Venture v. United States.Continue Reading Contractor’s $10.5 Million Differing Site Condition Claim Torpedoed

Contractor claims for differing site conditions remain fairly common. There are two types of DSC claims. Under a Type I claim, a contractor can obtain additional time and compensation where the contractor encounters a subsurface or latent physical condition at the project site that differs materially from the conditions indicated in the parties’ contract.

For example, contractors have successfully asserted Type I claims where the contractor encountered a groundwater table that was higher than indicated in the contract documents while performing underground work.

With a Type II claim, a contractor may be entitled to additional time and compensation where there are unknown and unusual physical conditions at the project site that differ materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the parties’ contract.

An example of a Type II condition may be where a contractor performing a job that requires soil work encounters tough soils that are more difficult to excavate than expected and no bidder, no matter how experienced, would have anticipated the conditions actually found.

If a contractor believes it is entitled to additional time and compensation on a project due to a DSC, the contractor should consider submitting a claim. There are four things a contractor should know about DSC claims:Continue Reading Four Things to Know About Differing Site Condition Claims

There are two types of differing site condition claims–Type I and Type II claims. Generally, a contractor may make a Type I differing site condition claim where the contractor encounters a subsurface or latent physical condition at the project site that differs materially from the conditions indicated in the parties’ contract.

Under a Type II claim, a contractor may assert a DSC claim where there are unknown and unusual physical conditions at the project site that differ materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the parties’ contract.

Both Type I and Type II DSC claims can be difficult to prove. Last week, after having a seven-day trial, a federal court rejected a subcontractor’s $2.4 million DSC claim in Phillips & Jordan, Inc. v. United States.Continue Reading Federal Court Rejects Subcontractor’s $2.4 Million Differing Site Condition Claim