If a construction contractor working on a federal government project is impacted by a government-caused change, the contractor must take steps to preserve its right to obtain additional compensation or time to complete the project. In particular, a contractor must comply with the contract’s claim process. (Click here for the six most common contractor claims.)

Generally, there are three steps to obtaining additional money or time on a federal government project:

1. Submit a request for equitable adjustment: If the government causes a change to the project, the contractor should submit an REA that explains the change, how that change has impacted the contractor’s work, the amount of additional money and/or time to which the contractor is entitled, and backup for the amounts claimed.

Although a contractor is not required to submit an REA before submitting a formal claim, contractors frequently submit the REA first, because it can serve as a starting point for the contractor and the contracting officer to negotiate. The main downside to submitting an REA rather than a claim is that interest will not to start running until a claim is submitted. Also, there is no deadline for the contracting officer to make a decision on an REA.Continue Reading How to Get More Money and Time on Federal Government Construction Projects

Change-in-scope claims are one of the most common contractor claims. Typically, scope disputes center on whether work that the owner directed a contractor to perform was part of the original scope of the contractor’s work. If it was part of the original scope, then the contractor may not be entitled to additional compensation or time to perform that work. But if it was out-of-scope work, it may be a breach of contract for the owner to refuse to pay for that work.

At times, scope disputes can result in the termination of the parties’ contract. That’s what happened in a recent dispute between the federal government and a contractor in GSC Construction, Inc. v. Secretary of Army.Continue Reading Federal Court Rejects Scope-Change and Time-Extension Claims

One common request that I get from my contractor clients is to determine whether a client has a legitimate claim for additional time and money due to impacts arising out of a project. While each situation is unique, there are typically four steps a contractor should take to evaluate a potential claim or dispute:
Continue Reading Four Steps for Evaluating Construction Claims on Public Projects

The coronavirus (COVID-19) is gaining speed and construction projects across the country and in Florida have reportedly been slowing or shut down as a result. It’s time for construction contractors, including those working on government projects, to consider whether they will be entitled to additional money and/or time on their projects. In this post, we will take a brief look at how things might shake out on federal government and Florida Department of Transportation (“FDOT”) projects.
Continue Reading Coronavirus and Government Construction Projects: Do Contractors Get More Money and Time?