Many construction payment disputes come down to one key question—who is responsible for extra costs incurred while building a project? Parties frequently have competing breach-of-contract actions that focus on who is liable. But a recent federal court case shows that you should not give short shrift to the damages that flow from the alleged breach.
In Barlovento, LLC v. AUI, Inc., Civ. No. 18-1112 GJF/JHR, 2021 WL 3879072 (D.N.M. Aug. 31, 2021), the United States Air Force awarded a general contractor a $5.5 million contract to renovate a taxiway at a military base. The general contractor then subcontracted the removal and replacement of the taxiway pavement and base course. This required the subcontractor to place three layers – subgrade, base course, and concrete.
The subcontractor fell behind in its performance of the work, and ultimately, the general contractor held a meeting with the subcontractor and a potential replacement subcontractor that would perform almost all the remaining work. At that meeting, the general contractor announced that it would take the concrete paving work away from the subcontractor. Despite the decision to de-scope the original subcontractor, the general contractor ended up terminating the subcontractor for default.Continue Reading General Contractor Awarded $22,000 of Its $1.3 Million Claim Against a Subcontractor