In construction disputes, one of the most important issues is whether the party claiming damages can adequately prove its damages at trial. Under Florida law, the burden is on the party seeking damages to prove its damages with a reasonable degree of certainty. While difficulty proving your damages may not be a bar to recovery, the award of damages cannot be based on mere speculation or guesswork. (For more on the burden of proof for construction damages under Florida law, click here.)

Florida law also specifies a “time of breach” standard that requires a party seeking damages based on defective construction work to calculate its damages as of the date of the breach of contract. A recent Florida appellate decision demonstrates the importance of proving damages under the time of breach standard.Continue Reading Court Reverses Award of Damages to Owners Due to Lack of Evidence

To win on a breach-of-contract claim, the party asserting the claim must prove that the other party to the contract caused the non-breaching party to incur damages. In construction disputes, the non-breaching party (e.g., a contractor or subcontractor) will often claim that it incurred lost profits due to the other party’s breach.

For example, if an owner wrongfully terminates a contractor, the contractor may be entitled to the profit that it was going to make on the project but for the owner’s termination of the contract. But to obtain those lost profits, the contractor will have to offer supporting evidence.Continue Reading How to Prove Lost Profits in Construction Disputes

If a project takes longer than expected due to unforeseeable reasons beyond the contractor’s control, then the contractor may have a delay claim against the owner. Typical delay-claim damages include extended general conditions, home office overhead, and financing costs.

Delay claims are one of the most common issues that arise on construction projects. Typically, the burden is on the contractor to prove a delay claim, and the contractor must prove the following three elements:

  1. the length of the delay;
  2. the causal link between the delay and the owner’s wrongful acts; and
  3. the harm to the contractor due to the delay (i.e., the contractor’s damages).

The second element can be the most difficult to prove. To show a causal link between the owner’s wrongful acts and the delay, the contractor must show that the owner’s actions affected the activities on the critical path of the project.Continue Reading No Critical Path Analysis for a Contractor Delay Claim? Expect Your Claim to Be Denied.