construction claims; acceleration claims

Many commercial construction contracts have deadlines for the contractor or subcontractor to complete its work. Typically, a contractor is entitled to the time allowed under the contract to finish its work. If a contractor is forced to complete its work earlier than the specified completion deadline, the contractor may be entitled to additional compensation for accelerating its work.

There are two types of acceleration–actual acceleration and constructive acceleration. Actual acceleration occurs when a contractor is expressly directed to pick up the pace of the work. Constructive acceleration happens when a contractor is entitled to a time extension, but the project owner refuses to give the time extension and requires the contractor to complete its work by the original deadline.

Continue Reading The Basics of Contractor Acceleration Claims